By the sound of it, you just want one activity to equal your total cost on the project. If you don't need to utilize the histograms, then just create a user defined field and call it "Total Expense Cost", and input the value to the activity that you desire.
Regards,
Patrick
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2020-04-14 14:20
Member for
5 years 5 monthsHi Usman,By the sound of it,
Hi Usman,
By the sound of it, you just want one activity to equal your total cost on the project. If you don't need to utilize the histograms, then just create a user defined field and call it "Total Expense Cost", and input the value to the activity that you desire.
Regards,
Patrick
Member for
16 years 3 monthscreate a LOE activity make
create a LOE activity
make the predcessors is a SS relationship with the 1st activity
make the successor a ff relationship with the last activity in the schedule
create a resource call it lumpsum
assign the resource to loe activity
add the cost for the project to the resource
then assign a curve to the resource