Creating deliverable milestones within a work activity....explained below.

Member for

21 years 8 months

As a workaround consider using FF links with ALAP logic.

ALAP-logic click the image and zoom.

Good Luck

Member for

16 years 3 months

you said "P6 did let me do it in one place not in others. I would like to understand why."

look at where it let you do it

what was the activity type

was the predcessors a SS realtionship ?

was the successor a FF relationship

was the precdessor a start milestone ?

was the predcesssor a finish milestone

was the successor a start milestone

was the successor a finish milestone ?

was the predcessor and or sucessor a LOE activitiy type. 

look at where it worked in detail and then look for any anomolies of where you want to use it again and see what the differences are. 

Member for

7 years 10 months

Thanks for replying. I did clarify in a second post but somewhere above, not sure how the forum posts work. I keep posting twice as well.

I think what you describe and say isnt allowed is what I described as the hammock activity. While I still don't see why it isn't allowed as it is a real situation - P6 did let me do it in one place not in others. I would like to understand why.

 

I don't like the option of placing them as work steps as we lose visability in the schedule. 

 

Thanks Agsin

Member for

7 years 10 months

OK, so i changed the activityies from milestons to activities. P6 allowed me (ONCE) to create a SS predecessor  and a FF successor with the main activity. However it allowed me to do it in one place but not in others. I read in an Old P3 textbook that this was a hammock activity / relationship.

What are the rules for creating this relationship. I do not see any difference bewteen the two areas of the schedule. one allows the other doesn't.  I thought it was that i used a milestone rather than a Task dependent activity type but that isnt the difference. 

Member for

18 years 11 months

Brian,

You seem to be attempting circular logic.  I.e. Work Activity >(SS)> Deliverable A >(FF)> Work Activity.  P6 won't let you do that.

Suggestions, either:

1. Break Work Activity into a Start portion and a Finish portion, then tie your deliverables in.

2. Enter your deliverables as Steps on the work activity rather than milestones.

Good luck, tom

Member for

16 years 3 months

make a new activity D give it 0 days but keep the activity tyep as TASK not start milestone then you can tie to this