Performance % Complete

Member for

16 years 3 months

yuo could create a new alctivity and give it the activity type as wbs summary 

Member for

6 years 9 months

Thanks Zoltan for this!  My follow up question is what do I need to make sure is included in the resource assignment to have it show as a summary on the WBS band?  I have resources assigned to all activity but no units because I don't want to double up on the $$ vaule in my schedule since the activity at the higher level WBS is holding the $$

Member for

16 years 3 months

Performance Percent Complete for the activity is based on Units Percent Complete. Activities without a Resource curve assigned to one or more of the Resource Assignments will use the Activity percent complete

so 100%+100%+100%+95%=395% 

or  =$1+$1+$1+.95=$3.95 ?

Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP • 100) divided by Budget at completion regardless of what earned value technique is selected for the activity's WBS. 

so =$1+$1+$1+.95=$3.95*100=$395/$400=$98.75