That is exactly what I am looking for. The linkage between each dicipline to one another plus the flow within each discipline. I am new to EPC work and I am trying to have a good understanding of the sequencing of drawings and such.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2019-07-31 14:35
typically EPC includes enginering procurement and construction
for for the E part of this you typically have a few major milestones for the design drawings and specifications which is the
30% completion
60% completion
90% completion
and IFC (issue for construction)
Typically each discipline would need information from the other so that they can continue with their portion of the design
For the P part procurement once you hit the 90% Design completion level or you can wait unilt ithe issuance of the IFC drawings thne purchasing can begin to buy out the LOP's large purchase orders and buy out the project
for the C part construction once you know what you are building you can begin to create the installation schedule and inorporate the dates that you got from the procurement to ensure that the materials and equipment will be there in time to support the installation.
Member for
6 years 5 monthsThanks, Joannes. I recently
Thanks, Joannes. I recently downloaded his book.
Member for
15 years 9 monthsHi EricI suggest to use the
Hi Eric
I suggest to use the book "The Oil & Gas Engineering guide 3rd Edition "by Herve Baron.
Regards
Johannes
Member for
6 years 5 monthsBryc, That is exactly what I
Bryc,
That is exactly what I am looking for. The linkage between each dicipline to one another plus the flow within each discipline. I am new to EPC work and I am trying to have a good understanding of the sequencing of drawings and such.
Member for
16 years 3 monthstypically EPC includes
typically EPC includes enginering procurement and construction
for for the E part of this you typically have a few major milestones for the design drawings and specifications which is the
30% completion
60% completion
90% completion
and IFC (issue for construction)
Typically each discipline would need information from the other so that they can continue with their portion of the design
For the P part procurement once you hit the 90% Design completion level or you can wait unilt ithe issuance of the IFC drawings thne purchasing can begin to buy out the LOP's large purchase orders and buy out the project
for the C part construction once you know what you are building you can begin to create the installation schedule and inorporate the dates that you got from the procurement to ensure that the materials and equipment will be there in time to support the installation.
Member for
16 yearsWhat you need exactelly ?
What you need exactelly ? there is a lot relation between the dicipline foir exemple Process and piping or civil work and equipement...