Thats not true out of sequence logic happens when you start an activity before its predecessor has completed.

Since this is a new activity all you are doing is inserting it and it has nothing to do with out of sequence

out of sequence example

install conduit finish to start relationship tp pulling wire

as you progress the schedule you have started conduit but you are not 100 % complete but you have started pulling wire

this is out of sequence progress

I do not know what out of sequence logic is 

it depends on where you insert this new activity as to if it pushes out the end date or not meaning where you assign it predcessor and its successor.