Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-06-14 14:18 Permalink Thats not true out of Thats not true out of sequence logic happens when you start an activity before its predecessor has completed. Since this is a new activity all you are doing is inserting it and it has nothing to do with out of sequence out of sequence example install conduit finish to start relationship tp pulling wire as you progress the schedule you have started conduit but you are not 100 % complete but you have started pulling wire this is out of sequence progress I do not know what out of sequence logic is it depends on where you insert this new activity as to if it pushes out the end date or not meaning where you assign it predcessor and its successor. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-06-14 14:18 Permalink Thats not true out of Thats not true out of sequence logic happens when you start an activity before its predecessor has completed. Since this is a new activity all you are doing is inserting it and it has nothing to do with out of sequence out of sequence example install conduit finish to start relationship tp pulling wire as you progress the schedule you have started conduit but you are not 100 % complete but you have started pulling wire this is out of sequence progress I do not know what out of sequence logic is it depends on where you insert this new activity as to if it pushes out the end date or not meaning where you assign it predcessor and its successor.
Member for
16 years 3 monthsThats not true out of
Thats not true out of sequence logic happens when you start an activity before its predecessor has completed.
Since this is a new activity all you are doing is inserting it and it has nothing to do with out of sequence
out of sequence example
install conduit finish to start relationship tp pulling wire
as you progress the schedule you have started conduit but you are not 100 % complete but you have started pulling wire
this is out of sequence progress
I do not know what out of sequence logic is
it depends on where you insert this new activity as to if it pushes out the end date or not meaning where you assign it predcessor and its successor.