This was a programme produced by a contractor and written into our subcontract not something that has been submitted for acceptance. Thanks for the clarity.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2019-04-12 13:30
The constrains in the schedule shoule be contractual ones. Either Contractual milestones or if you are give release dates for certain areas. ALL CONTRACTUAL
Member for
6 years 7 monthsThis was a programme produced
This was a programme produced by a contractor and written into our subcontract not something that has been submitted for acceptance. Thanks for the clarity.
Member for
16 years 3 monthsMike is correct The
Mike is correct
The constrains in the schedule shoule be contractual ones. Either Contractual milestones or if you are give release dates for certain areas. ALL CONTRACTUAL
Member for
19 years 10 monthsHi Matthew - Welcome to
Hi Matthew - Welcome to Planning Planet.
Just admit the mistake and submit the corrected programme.
And while you are at it take those constraints off - they shouldn't be there.
Best regards
Mike Testro