Initial programme included within contact was not rescheduled before issuing

Member for

6 years 7 months

This was a programme produced by a contractor and written into our subcontract not something that has been submitted for acceptance. Thanks for the clarity.

Member for

16 years 3 months

Mike is correct 

The constrains in the schedule shoule be contractual ones. Either Contractual milestones or if you are give release dates for certain areas. ALL CONTRACTUAL

Member for

19 years 10 months

Hi Matthew - Welcome to Planning Planet.

Just admit the mistake and submit the corrected programme.

And while you are at it take those constraints off - they shouldn't be there.

Best regards

Mike Testro