Simply because you don't want to reveal costs. More man-hours mean more costs and perhaps more profits. Or perhaps "man-hours" is one of the many ways in hiding profits. You can also use volume or quantity of works, but you must end up with a common unit in order to summarize or capture WBS or hierarchical lines. Therefore, you will need man-hours or currencies as common unit. Wondering why "physical percent complete" do not summarize by itself in a software?
Member for
19 years 1 monthSimply because you don't want
Simply because you don't want to reveal costs. More man-hours mean more costs and perhaps more profits. Or perhaps "man-hours" is one of the many ways in hiding profits. You can also use volume or quantity of works, but you must end up with a common unit in order to summarize or capture WBS or hierarchical lines. Therefore, you will need man-hours or currencies as common unit. Wondering why "physical percent complete" do not summarize by itself in a software?