Remaining Late Unit tabulated based on Early Finish Date

Member for

16 years 3 months

if there is 0 float then the Late Start and early start must be the SAME this is the definition of 0 float

so the late start CAN NOT BE it should be later than early start date if the float is 0.

check your remaining durations turn on your decimal places (this is under edit user preferences time unist tab duration format)

and make sure that the rmaing durations are whole numbers if the are not this can cause a 1 day activity to be spread over 2 dasys. and a 2 day actvity to be spread over 3 days etc. This is bacuse the activity starts on the 1st day and finishes by noon on the next day which causes the successor to start on noon and finish on noon the NEXT day. 

Member for

6 years 10 months

Hi Zoltan.

There is no 0 float, and I checked the late start it should be later than early start date. 

But the problem already solve. I tried change duration for one activity, reschedule, and then change the activity's duration back to the original one, and reschedule again. Then only the resource assignment is correct. I don't know why but maybe it's because the primavera version I'm using is not stable.

 

Thanks by the way

Member for

16 years 3 months

if the total float is zero then they should be the same