As-built Time-Chainage Chart

Member for

20 years 6 months

Dave,

Just to update this, a recent release of Turbo-Chart now lets charts be drawn with tasks defined down to hours and minutes accuracy when displaying days as the timescale units.

Please be in touch if you need any assistance.

Member for

16 years 3 months

why not use excel ?

Member for

20 years 6 months

Here's a sneak peak of what Turbo-Chart was able to produce, in a matter of minutes withthe As-Build data prepared in the Construction Log.

[[wysiwyg_imageupload:6211:]]

Member for

20 years 6 months

Abdulrahman, do you mean to compare as-built vs planned? That can be easily done. Please contact me offline, perhaps with a sample of your data and I'll demonstrate it.

Regards
Santosh.

Member for

10 years 6 months

Thanks Santosh, 

This is nice software, but unfortunately I need something different, because its produce chart in simple schematic way for planned main subjects. 

And I need chart for as built data which would be more detailed (as example: in the needed chart, we could have many repetative (overlaps) activities on the same chainages but would be in different levels in chart according to the time (y axis) that they had been executed.

Member for

20 years 6 months

Abdulrahman,

Bit biased in my response here but...