Planning, Scheduling & Programming Discussion Member for 24 years 9 months Member for 24 years 9 months Submitted by Patrick Weaver on Sat, 2014-11-15 10:14 Permalink Nader,Unless there is a Nader, Unless there is a contractual requirement to use a particular WBS template (which will be provided), the WBS needs to reflect ho the work of the project will be managed, see: http://www.mosaicprojects.com.au/WhitePapers/WP1011_WBS.pdf Log in or register to post comments
Member for 24 years 9 months Member for 24 years 9 months Submitted by Patrick Weaver on Sat, 2014-11-15 10:14 Permalink Nader,Unless there is a Nader, Unless there is a contractual requirement to use a particular WBS template (which will be provided), the WBS needs to reflect ho the work of the project will be managed, see: http://www.mosaicprojects.com.au/WhitePapers/WP1011_WBS.pdf
Member for
24 years 9 monthsNader,Unless there is a
Nader,
Unless there is a contractual requirement to use a particular WBS template (which will be provided), the WBS needs to reflect ho the work of the project will be managed, see: http://www.mosaicprojects.com.au/WhitePapers/WP1011_WBS.pdf