MEP Sequence

Member for

16 years 3 months

conduit, wire then terminations

in slab would be first

then the highest component in the ceiling 

then any in-wall work 

Member for

16 years 3 months

conduit, wire then terminations

in slab would be first

then the highest component in the ceiling 

then any in-wall work 

Member for

19 years 10 months

Hi Project

That is too much detail.

You need to split the MEP into 3 tasks - Ducting > Pipework> Containment.

These are place vertically in risers and horizontally in ceiling zones and / or floor zones.

Cables are placed in the containment after weather tight conditions.

IT cables have seperate containment and must not be placed close to HV / LV cables.

Best regards

Mike Testro