Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2014-10-21 13:14 Permalink conduit, wire then conduit, wire then terminations in slab would be first then the highest component in the ceiling then any in-wall work Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2014-10-21 13:14 Permalink conduit, wire then conduit, wire then terminations in slab would be first then the highest component in the ceiling then any in-wall work Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2014-10-19 22:01 Permalink Hi ProjectThat is too much Hi Project That is too much detail. You need to split the MEP into 3 tasks - Ducting > Pipework> Containment. These are place vertically in risers and horizontally in ceiling zones and / or floor zones. Cables are placed in the containment after weather tight conditions. IT cables have seperate containment and must not be placed close to HV / LV cables. Best regards Mike Testro Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2014-10-21 13:14 Permalink conduit, wire then conduit, wire then terminations in slab would be first then the highest component in the ceiling then any in-wall work
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2014-10-21 13:14 Permalink conduit, wire then conduit, wire then terminations in slab would be first then the highest component in the ceiling then any in-wall work
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2014-10-19 22:01 Permalink Hi ProjectThat is too much Hi Project That is too much detail. You need to split the MEP into 3 tasks - Ducting > Pipework> Containment. These are place vertically in risers and horizontally in ceiling zones and / or floor zones. Cables are placed in the containment after weather tight conditions. IT cables have seperate containment and must not be placed close to HV / LV cables. Best regards Mike Testro
Member for
16 years 3 monthsconduit, wire then
conduit, wire then terminations
in slab would be first
then the highest component in the ceiling
then any in-wall work
Member for
16 years 3 monthsconduit, wire then
conduit, wire then terminations
in slab would be first
then the highest component in the ceiling
then any in-wall work
Member for
19 years 10 monthsHi ProjectThat is too much
Hi Project
That is too much detail.
You need to split the MEP into 3 tasks - Ducting > Pipework> Containment.
These are place vertically in risers and horizontally in ceiling zones and / or floor zones.
Cables are placed in the containment after weather tight conditions.
IT cables have seperate containment and must not be placed close to HV / LV cables.
Best regards
Mike Testro