Activities Spanning More Days than it should in a Primavera P6 Schedule

Member for

7 years 9 months

Hi All,
 
An innovative product line of Oracle Primavera enhancements and add-ons unique to Emerald Associates. Our clients come to us with Primavera problems, and we create tools to solve them.Emerald Tools - Primavera Enhancements and Add-Ons

You may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk

Member for

16 years 3 months

it has to do with times tunr on your times go to edit uses preference and turn on the times. 

also in there set the duration dispaly to 2 decimals as you may have soem activites that are not whole days.

any start milestones the TIME should be set to 8:00 am or the start of the day for the calendar that it is on.

any finish milestones the TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this milestone is on.

also any start constraints the TIME should be set to 8:00 am or the start of the day for the calendar that this activity is on

also any finish constraints the TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this activity is on.

also ALL actual start TIMES should be  set to 8:00 am or the start of the day for the calendar that this activity is on

also ALL actual fininsh TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this activity is on.

Member for

24 years 9 months

The problem is almost always in the calendars - different number of hours in a day, different start times in a day, or simply a predecessor finishing half way through a day.