The problem is almost always in the calendars - different number of hours in a day, different start times in a day, or simply a predecessor finishing half way through a day.
Member for
7 years 9 monthsHi All, An innovative product
You may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk
Member for
16 years 3 monthsit has to do with times tunr
it has to do with times tunr on your times go to edit uses preference and turn on the times.
also in there set the duration dispaly to 2 decimals as you may have soem activites that are not whole days.
any start milestones the TIME should be set to 8:00 am or the start of the day for the calendar that it is on.
any finish milestones the TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this milestone is on.
also any start constraints the TIME should be set to 8:00 am or the start of the day for the calendar that this activity is on
also any finish constraints the TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this activity is on.
also ALL actual start TIMES should be set to 8:00 am or the start of the day for the calendar that this activity is on
also ALL actual fininsh TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this activity is on.
Member for
24 years 9 monthsThe problem is almost always
The problem is almost always in the calendars - different number of hours in a day, different start times in a day, or simply a predecessor finishing half way through a day.