Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sat, 2016-11-05 12:40 Permalink Hi MDThe text is a clumsy Hi MD The text is a clumsy description of a Time Impact Analysis. Global claims always fail in a tribunal but they can be a useful negotiating tool. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sat, 2016-11-05 12:40 Permalink Hi MDThe text is a clumsy Hi MD The text is a clumsy description of a Time Impact Analysis. Global claims always fail in a tribunal but they can be a useful negotiating tool. Best regards Mike Testro
Member for
19 years 10 monthsHi MDThe text is a clumsy
Hi MD
The text is a clumsy description of a Time Impact Analysis.
Global claims always fail in a tribunal but they can be a useful negotiating tool.
Best regards
Mike Testro