Can I get new unit price in the re-measure contract?

Member for

19 years 10 months

Hi Bernadette

There are provisions in most contracts for price revisions in case of variation orders but increased quantitiees are not automatically variations.

Other terms state that increase or decrease in quantities within a percentage band do not warrant unit price changes.

The change in a unit price is necessary to adjust the recovery of fixed cost elements in a volume and time related price.

For instance the unit price of insitu concrete may well include the fixed cost of setting up a batching plant and deploying haul trucks.

If there is less concrete than initially measured then the fixed costs will not be fully recovered and if there is more then the cost will be over recovered - hence the need for an adjustment.

Best regards

Mike Testro

Member for

18 years 5 months

Hi Mike,

Isnt it that the premise of a re-measurement contract is that "contract" quantities are deemed provisional except for the unit rates which are fixed? Therefore, in Ayman's case, he can get a new unit price for a (new) work item not identified in the contract. 

Any "drastic" increase or decrease in quantities given the fixed unit rate could be a risk either by the owner or contractor. 

Im not familiar with the different contract provisions of a re-measurement contract wherein unit rates could be changed, can you give examples?

Apologies for the lateness of my comment/s. Newbie here

 

Cheers,

Bernadette

Member for

19 years 10 months

Hi Ayman

Probably yes - depending on the terms of the contract - but in case of a "drastic increase" in quantities then be prepared for a reduction in unit prices.

Best regards

Mike Testro