Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2008-07-16 09:57 Permalink RE: ENGINEERING CLAIM Hi Jorge You do not say if you are trying to claim for extra time or money. As always it all depends on what it says in the contract. Usually extra work is recoverable in both time and money unless the Contractor has agreed to take on the risk. Best regards Mike T. Member for 19 years 9 months Member for 19 years 9 months Submitted by khawaja uddin on Wed, 2008-07-16 04:06 Permalink RE: ENGINEERING CLAIM Hi, you can prepare your claim as a DAY WORK ,which includes the work you have done on certain dates and the eng. hr spent perform the work . Hope it may help you . Rgds Member for 21 years 11 months Member for 22 years Submitted by JORGE FIERRO on Tue, 2008-07-15 16:07 Permalink RE: ENGINEERING CLAIM Thanks Omer, The question should be: Is it possible to structure a claim for increased quiantity of engineering (more piping, concrete, cables, etc...), without changes in the scope of work ? If yes, please an example. Thanks, Jorge Member for 17 years 4 months Member for 17 years 4 months Submitted by Omer Hassan on Tue, 2008-07-15 13:47 Permalink RE: ENGINEERING CLAIM Can u please elaborate your question? Regards, Omer Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2008-07-16 09:57 Permalink RE: ENGINEERING CLAIM Hi Jorge You do not say if you are trying to claim for extra time or money. As always it all depends on what it says in the contract. Usually extra work is recoverable in both time and money unless the Contractor has agreed to take on the risk. Best regards Mike T.
Member for 19 years 9 months Member for 19 years 9 months Submitted by khawaja uddin on Wed, 2008-07-16 04:06 Permalink RE: ENGINEERING CLAIM Hi, you can prepare your claim as a DAY WORK ,which includes the work you have done on certain dates and the eng. hr spent perform the work . Hope it may help you . Rgds
Member for 21 years 11 months Member for 22 years Submitted by JORGE FIERRO on Tue, 2008-07-15 16:07 Permalink RE: ENGINEERING CLAIM Thanks Omer, The question should be: Is it possible to structure a claim for increased quiantity of engineering (more piping, concrete, cables, etc...), without changes in the scope of work ? If yes, please an example. Thanks, Jorge
Member for 17 years 4 months Member for 17 years 4 months Submitted by Omer Hassan on Tue, 2008-07-15 13:47 Permalink RE: ENGINEERING CLAIM Can u please elaborate your question? Regards, Omer
Member for
19 years 10 monthsRE: ENGINEERING CLAIM
Hi Jorge
You do not say if you are trying to claim for extra time or money.
As always it all depends on what it says in the contract.
Usually extra work is recoverable in both time and money unless the Contractor has agreed to take on the risk.
Best regards
Mike T.
Member for
19 years 9 monthsRE: ENGINEERING CLAIM
Hi,
you can prepare your claim as a DAY WORK ,which includes the work you have done on certain dates and the eng. hr spent perform the work .
Hope it may help you .
Rgds
Member for
21 years 11 monthsRE: ENGINEERING CLAIM
Thanks Omer,
The question should be:
Is it possible to structure a claim for increased quiantity of engineering (more piping, concrete, cables, etc...), without changes in the scope of work ?
If yes, please an example.
Thanks,
Jorge
Member for
17 years 4 monthsRE: ENGINEERING CLAIM
Can u please elaborate your question?
Regards,
Omer