ENGINEERING CLAIM

Member for

19 years 10 months

Hi Jorge



You do not say if you are trying to claim for extra time or money.



As always it all depends on what it says in the contract.



Usually extra work is recoverable in both time and money unless the Contractor has agreed to take on the risk.



Best regards



Mike T.

Member for

19 years 9 months

Hi,

you can prepare your claim as a DAY WORK ,which includes the work you have done on certain dates and the eng. hr spent perform the work .

Hope it may help you .

Rgds

Member for

21 years 11 months

Thanks Omer,



The question should be:



Is it possible to structure a claim for increased quiantity of engineering (more piping, concrete, cables, etc...), without changes in the scope of work ?



If yes, please an example.



Thanks,



Jorge

Member for

17 years 4 months

Can u please elaborate your question?



Regards,

Omer