In a lump sum contract, the Contractor should during the biding stage requested information on this issue, if not indicated in the Specs and drawings.
In addition, should there is plaster above F.C., for which I believe there is not, I agree that the Employer has the right to omit part of the works. Nevertheless, the Employer may require time saving for deleting such item depending on the amount of works of the same
Generally, in the areas where it is specified to have false ceiling, no need to have plaster for the ceiling above, only maybe 10 - 15 cm high along the wall cornice above the false ceiling level only for the appearance, but in rare cases it might be specified otherwise.
I guess I dont have standard description for both kind of ceilings, but by definition I understand, the Structural ceiling has a structural function such as carrying dead and live loads of the structure, and the false ceiling it has mainly Architectural function.
I dont understand, how it is not mentioned and the Contractor insists to carryout plaster for the ceiling and walls above the False ceiling level!!, anyhow in any case the Client would have the right to instruct omission of such plaster and the respective unit rate would be revised accordingly.
Member for
20 years 3 monthsRE: Celing Plaster above False Celing ( around walls also )
Dear all,
In a lump sum contract, the Contractor should during the biding stage requested information on this issue, if not indicated in the Specs and drawings.
In addition, should there is plaster above F.C., for which I believe there is not, I agree that the Employer has the right to omit part of the works. Nevertheless, the Employer may require time saving for deleting such item depending on the amount of works of the same
Hope that the above replies your querries.
regards
Member for
18 years 5 monthsRE: Celing Plaster above False Celing ( around walls also )
Hi
Generally, in the areas where it is specified to have false ceiling, no need to have plaster for the ceiling above, only maybe 10 - 15 cm high along the wall cornice above the false ceiling level only for the appearance, but in rare cases it might be specified otherwise.
I guess I dont have standard description for both kind of ceilings, but by definition I understand, the Structural ceiling has a structural function such as carrying dead and live loads of the structure, and the false ceiling it has mainly Architectural function.
I dont understand, how it is not mentioned and the Contractor insists to carryout plaster for the ceiling and walls above the False ceiling level!!, anyhow in any case the Client would have the right to instruct omission of such plaster and the respective unit rate would be revised accordingly.
Anybody would have opposite opinion?
Thanks