I see you posted this question some time ago. I have dealt with offshore EPIC contracts, similar to your EPC type. If you are still looking for pointers, get in touch.
Member for
23 years 9 months
Member for23 years9 months
Submitted by Keith Pickavance on Fri, 2005-03-04 06:28
Andrew, you might like to consider the content of the PFE Change Management Supplements, written to enable the JCT forms of contract to be SCL Protocol compliant. You can download a specimen of that for JCT98 from www.pickavance.net. Although set out for JCT98, the principles can be applied to any contract. See also the guidance notes which explian the principles.
Member for
20 years 10 monthsRE: Planning / scheduling section in contract
I see you posted this question some time ago. I have dealt with offshore EPIC contracts, similar to your EPC type. If you are still looking for pointers, get in touch.
Member for
23 years 9 monthsRE: Planning / scheduling section in contract
Andrew, you might like to consider the content of the PFE Change Management Supplements, written to enable the JCT forms of contract to be SCL Protocol compliant. You can download a specimen of that for JCT98 from www.pickavance.net. Although set out for JCT98, the principles can be applied to any contract. See also the guidance notes which explian the principles.