Collapse completed summary tasks only

Member for

19 years 8 months

Dariusz,

You can if you make a small compromise and that is not showing the completed tasks under an incomplete summary.

The filter would be 

[[wysiwyg_imageupload:8036:]]

Criteria 1 - Summary Tasks with Task Progress Completed

Criteria 2 - Tasks or Milestones or Summary Tasks with Task Progress Specific Progress Amount Less Than 100%

Also, Objects must meet ANY criteria

Otherwise, I'm sure you could write an SQL statement but not sure I can help you with that.

Let me know if that works for you.

Kind regards,

Konstantinos

Member for

19 years 10 months

Sorry Dariusz

You have to do it manually.

One Click and save is all you need.

You don't have to show all your sub tasks.

You can have a sub summary labelledd 100% and move every complted task down into that showing only the work in prgress.

Best regards

Mike T.