When you have more than one task in a single row just click the small + sign on the left of the title and the tasks will drop down into sequences showing a single UTID. You may have to unclick the "Task per Line" button on the Format Bar Chart menu to make this work.
You me have already resolved this but the easiest method might be to change the column details in Table Definition - hit ‘Settings’ against Specific Task, select the ‘Specific Task’ radio button and specify Task Number ‘1’.
The column will then only return the UTID for the first task in any multi task bars.
Member for
19 years 10 monthsHi ChrisWhen you have more
Hi Chris
When you have more than one task in a single row just click the small + sign on the left of the title and the tasks will drop down into sequences showing a single UTID. You may have to unclick the "Task per Line" button on the Format Bar Chart menu to make this work.
Best regards Mike Testro
Member for
15 years 3 monthsChris, You me have already
Chris,
You me have already resolved this but the easiest method might be to change the column details in Table Definition - hit ‘Settings’ against Specific Task, select the ‘Specific Task’ radio button and specify Task Number ‘1’.
The column will then only return the UTID for the first task in any multi task bars.