Need help with Asta "logic"

Member for

19 years 10 months

Hi Andrea
There may be a conflict with your calendars - particularly if you have resource modelling in place using their own calendar.
Check if your summary bars have any logic attached. This distorts the task logic and should be removed.
It is possible that you have a logic flaw in that particular file.
Open a new blank project and copy - paste the old programme entirely into the new.
Finally Asta Project Support is always available by phone or email.
Best regards
Mike Testro

Member for

24 years 5 months

Check activity constraints there may be a "Finish on" hard constraint.

Member for

8 years 1 month

Hello. 

Your suggestion didn't result in any change but when i changed the "status line" in the options below that tick box the activity jumped forward to its more logical position. I find this very curious as the logic should have placed it after its predessecors no matter what date the status line has. 

Member for

19 years 10 months

Hi Andrea

There is an option in reschedule that allows "Link around completed tasks" try that.

Best regards

Mike T.