Asta Powerproject Member for 10 years 3 months Member for 10 years 3 months Submitted by Yasine on Mon, 2017-07-24 13:35 Permalink Hi Mike,Thank you for your Hi Mike, Thank you for your input, helpful as always. Regards Yas. Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2017-07-23 12:24 Permalink Hi YasineJust copy paste the Hi Yasine Just copy paste the Pre Construction file onto the Construction Programme and turn them both into "Is A Project". You can then link them at any level and display any views of the two files on one display. in effect you can have any number of projects in the one file and you can then display the RAG dots for the whole company. You can also resource level key resource elements across the whole work force on every project. Best regards Mike T. Log in or register to post comments
Member for 10 years 3 months Member for 10 years 3 months Submitted by Yasine on Mon, 2017-07-24 13:35 Permalink Hi Mike,Thank you for your Hi Mike, Thank you for your input, helpful as always. Regards Yas.
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2017-07-23 12:24 Permalink Hi YasineJust copy paste the Hi Yasine Just copy paste the Pre Construction file onto the Construction Programme and turn them both into "Is A Project". You can then link them at any level and display any views of the two files on one display. in effect you can have any number of projects in the one file and you can then display the RAG dots for the whole company. You can also resource level key resource elements across the whole work force on every project. Best regards Mike T.
Member for
10 years 3 monthsHi Mike,Thank you for your
Hi Mike,
Thank you for your input, helpful as always.
Regards
Yas.
Member for
19 years 10 monthsHi YasineJust copy paste the
Hi Yasine
Just copy paste the Pre Construction file onto the Construction Programme and turn them both into "Is A Project".
You can then link them at any level and display any views of the two files on one display.
in effect you can have any number of projects in the one file and you can then display the RAG dots for the whole company.
You can also resource level key resource elements across the whole work force on every project.
Best regards
Mike T.