Making it into a buffer task will only affect the start of the buffer task depending on the movement of its predeccesor, the back end of the buffer task will have a deadline constraint applied to it. What if i want the completion of a seperate task to drive the completion of a the buffer task (with a FF link)?
So i will have two task with a gap between them. The tasks may fluctuate in terms of start/completion dates, but a seperate task linked in between them will automatically fluctuate in duration along with them, to replace the gap between the two task.
Member for
24 years 5 monthsThe Hammock type activity
The Hammock type activity will work if task 1 and 3 are both milestones. Add them to a hammock activity called Guard delivered building material
Member for
19 years 10 monthsHi BenA buffer task is
Hi Ben
A buffer task is infinitely flexible between the movement of the start and finish links depending on both upstream and downstream movement.
What more do you want?
Best regards
Mike T.
Member for
9 years 3 monthsHi Mike, Making it into a
Hi Mike,
Making it into a buffer task will only affect the start of the buffer task depending on the movement of its predeccesor, the back end of the buffer task will have a deadline constraint applied to it. What if i want the completion of a seperate task to drive the completion of a the buffer task (with a FF link)?
So i will have two task with a gap between them. The tasks may fluctuate in terms of start/completion dates, but a seperate task linked in between them will automatically fluctuate in duration along with them, to replace the gap between the two task.
Member for
19 years 10 monthsHi BenUse a BUFFER task.Creat
Hi Ben
Use a BUFFER task.
Creat a normal task using FS links and then Make Into> Buffer.
This is unique to Asta and does precisely what you wish.
There is an option to make it critical or not.
Best regards
Mike Testro
Member for
9 years 5 monthsHi Ben,I would have thought
Hi Ben,
I would have thought Asta has "Level of Effort" type tasks......?