Asta Powerproject Member for 18 years 5 months Member for 18 years 6 months Submitted by Chris Lothian on Tue, 2016-11-15 17:43 Permalink This might This might work.... If(SubType=SummaryType, "", switch( PlannedPercentComplete(CB,na)>PercentComplete,high,PlannedPercentComplete(CB,na)<=PercentComplete,low)) Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2016-09-28 15:06 Permalink Hi SamThe fact that the tick Hi Sam The fact that the tick appears on summary bars is highly beneficial in that it allows you drill down through the summaries to find the problem task. It is about time that Asta made the formula's more simple to administer by using a series of choices in drop down format. Best regards Mike Testro Log in or register to post comments
Member for 18 years 5 months Member for 18 years 6 months Submitted by Chris Lothian on Tue, 2016-11-15 17:43 Permalink This might This might work.... If(SubType=SummaryType, "", switch( PlannedPercentComplete(CB,na)>PercentComplete,high,PlannedPercentComplete(CB,na)<=PercentComplete,low))
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2016-09-28 15:06 Permalink Hi SamThe fact that the tick Hi Sam The fact that the tick appears on summary bars is highly beneficial in that it allows you drill down through the summaries to find the problem task. It is about time that Asta made the formula's more simple to administer by using a series of choices in drop down format. Best regards Mike Testro
Member for
18 years 5 monthsThis might
Member for
19 years 10 monthsHi SamThe fact that the tick
Hi Sam
The fact that the tick appears on summary bars is highly beneficial in that it allows you drill down through the summaries to find the problem task.
It is about time that Asta made the formula's more simple to administer by using a series of choices in drop down format.
Best regards
Mike Testro