Duration automatically changing from 1d to 6000w

Member for

9 years 6 months

Hi, 

Check if you have resources in the particular activites and been closed on single day span (Act Start-Finish) it accumulates your planned resource distributio and distort the complete timeline. I just am putting my guess as it occers here in my Schedule several times when we close DELETED Provisional sums acitviities with cost loaded into it.

 

Regards,

Ameya

Member for

19 years 10 months

Hi Stephen - welcome to planning planet

Never heard of that one before - have you created a buffer task by accident - if so change it back to a normal task.

Next check your calendars both on the task and any resources.

Can you change it back to 1d by either:

Change the dates in the spreadsheet?

Drag the task back with the mouse?

You could have a glitch on the software - try deleting the task and putting it on a new row.

If nothing else then contact Asta Support - I presume you have an up to date licence.