Asta Powerproject Member for 11 years 1 month Member for 11 years 1 month Submitted by Ryan_W on Thu, 2015-04-16 16:30 Permalink I don't want to show any I don't want to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration. Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2015-04-16 15:22 Permalink Hi RyanThis is too big a Hi Ryan This is too big a topic for exchange here. Go to Help and search on Histograms. Select "Introduction to Histograms" and start from there. Best regards Mike Testro Member for 11 years 1 month Member for 11 years 1 month Submitted by Ryan_W on Thu, 2015-04-16 12:33 Permalink Hi Mike, Thanks for your Hi Mike, Thanks for your response, but I'm struggling a little here. Any chance you can help me with a walkthrough of what I'm meant to do? This is the first histogram I've ever done and haven't a clue... Kind regards, Ryan Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2015-04-16 10:57 Permalink Hi RyanAsta software will do Hi Ryan Asta software will do this for you. Create a histogram with the selected data. Right click the histogram and select S-Curve - the graph will be created in Excell. Best regards Mike Testro Log in or register to post comments
Member for 11 years 1 month Member for 11 years 1 month Submitted by Ryan_W on Thu, 2015-04-16 16:30 Permalink I don't want to show any I don't want to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2015-04-16 15:22 Permalink Hi RyanThis is too big a Hi Ryan This is too big a topic for exchange here. Go to Help and search on Histograms. Select "Introduction to Histograms" and start from there. Best regards Mike Testro
Member for 11 years 1 month Member for 11 years 1 month Submitted by Ryan_W on Thu, 2015-04-16 12:33 Permalink Hi Mike, Thanks for your Hi Mike, Thanks for your response, but I'm struggling a little here. Any chance you can help me with a walkthrough of what I'm meant to do? This is the first histogram I've ever done and haven't a clue... Kind regards, Ryan
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2015-04-16 10:57 Permalink Hi RyanAsta software will do Hi Ryan Asta software will do this for you. Create a histogram with the selected data. Right click the histogram and select S-Curve - the graph will be created in Excell. Best regards Mike Testro
Member for
11 years 1 monthI don't want to show any
I don't want to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.
Member for
19 years 10 monthsHi RyanThis is too big a
Hi Ryan
This is too big a topic for exchange here.
Go to Help and search on Histograms.
Select "Introduction to Histograms" and start from there.
Best regards
Mike Testro
Member for
11 years 1 monthHi Mike, Thanks for your
Hi Mike,
Thanks for your response, but I'm struggling a little here.
Any chance you can help me with a walkthrough of what I'm meant to do?
This is the first histogram I've ever done and haven't a clue...
Kind regards,
Ryan
Member for
19 years 10 monthsHi RyanAsta software will do
Hi Ryan
Asta software will do this for you.
Create a histogram with the selected data.
Right click the histogram and select S-Curve - the graph will be created in Excell.
Best regards
Mike Testro