Hi Karol - welcome to planning planet.

That is very neat - thank you.

it's great to learn something new so early in the day - keep up the good threads.

Best regards

Mike Testro

Member for

11 years 11 months

Hi Chris,

If you want to copy filter sort/group and tables (which view consist of) to existing file - just go to Library Explorer, Display "Filter" "Group/Sort" and "Table Definition" - right click on selected filter sort/group, tables or whole folders and paste into new file's library explorer - same place. 

Whole views cant be copied from one file to another.

Karol 

Member for

12 years 9 months

Thanks Mike

Thats the easy way in Asta . Isnt?

 But in P6, we can easily import layouts and filters in any new project. So any such option is still not available in Asta?

If any, please share.

Member for

19 years 10 months

Hi Chris

Save the file with a new name and delete all the tasks you don't need.

Best regards

Mike Testro