Asta Power v11 - Progress line not transferring when imported in P6 v 6.2

Member for

19 years 11 months

Hi Emmanuelle

The transfer between Asta and P6 is never perfect and small adjustments sometimes have to be made - particularly with calendars.

So i suggest you reset the progress line in P6 to the required date and check for any other peculiarities.

Best regards

Mike Testro