Importing form one product to another will usually give a different answer unless the schedules are very simple as they all have different algorithums.
It is my experiance that Asta does this far better than any of the other products but manual intervention is usually required when going from one product to another.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
Member for
24 years 7 monthsImporting form one product to
Importing form one product to another will usually give a different answer unless the schedules are very simple as they all have different algorithums.
It is my experiance that Asta does this far better than any of the other products but manual intervention is usually required when going from one product to another.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com
www.primavera.com.au - a Primavera scheduling software resources site