Asta Powerproject Member for 13 years 4 months Member for 13 years 4 months Submitted by Ronan on Sun, 2012-07-08 11:50 Permalink V 11 V 11 Member for 13 years 4 months Member for 13 years 4 months Submitted by PlanEng on Sat, 2012-07-07 23:15 Permalink Ronan Niland, are you using Ronan Niland, are you using v11 or v12? Member for 15 years 5 months Member for 15 years 5 months Submitted by Chris Rymer on Tue, 2012-06-26 14:37 Permalink RonanTo turn the dialogue box Ronan To turn the dialogue box back on (in Version 12) go to File - Options - General. On the right hand side is a button called Do not show again prompts.... Click on this and select the Reset button. This will will restore the box you are after. Regards Chris Rymer Member for 19 years 11 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2012-06-21 18:13 Permalink Hi Ronan There are two sets Hi Ronan There are two sets of adjustments - assuming you are using the Icons and not that horible ribbon. 1. Tools > Options > Reschedule to set the progres line reschedule date. 2. Format > Barchart > Progress to turn the line display on or off plus other toggles. Best regards Mike Testro Log in or register to post comments
Member for 13 years 4 months Member for 13 years 4 months Submitted by Ronan on Sun, 2012-07-08 11:50 Permalink V 11 V 11
Member for 13 years 4 months Member for 13 years 4 months Submitted by PlanEng on Sat, 2012-07-07 23:15 Permalink Ronan Niland, are you using Ronan Niland, are you using v11 or v12?
Member for 15 years 5 months Member for 15 years 5 months Submitted by Chris Rymer on Tue, 2012-06-26 14:37 Permalink RonanTo turn the dialogue box Ronan To turn the dialogue box back on (in Version 12) go to File - Options - General. On the right hand side is a button called Do not show again prompts.... Click on this and select the Reset button. This will will restore the box you are after. Regards Chris Rymer
Member for 19 years 11 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2012-06-21 18:13 Permalink Hi Ronan There are two sets Hi Ronan There are two sets of adjustments - assuming you are using the Icons and not that horible ribbon. 1. Tools > Options > Reschedule to set the progres line reschedule date. 2. Format > Barchart > Progress to turn the line display on or off plus other toggles. Best regards Mike Testro
Member for
13 years 4 monthsV 11
V 11
Member for
13 years 4 monthsRonan Niland, are you using
Ronan Niland, are you using v11 or v12?
Member for
15 years 5 monthsRonanTo turn the dialogue box
Ronan
To turn the dialogue box back on (in Version 12) go to File - Options - General. On the right hand side is a button called Do not show again prompts.... Click on this and select the Reset button. This will will restore the box you are after.
Regards
Chris Rymer
Member for
19 years 11 monthsHi Ronan There are two sets
Hi Ronan
There are two sets of adjustments - assuming you are using the Icons and not that horible ribbon.
1. Tools > Options > Reschedule to set the progres line reschedule date.
2. Format > Barchart > Progress to turn the line display on or off plus other toggles.
Best regards
Mike Testro