How can I display cost centres columns

Member for

19 years 10 months

Hi Dumitru

Right click on a column > open table definition > add a column > scroll down to Cost > open Cost box on the right > select the cost head or All if you have a lost of cost heads > apply & close.

Best regards

Mike Testro