Can you copy views from one programme to another.

Member for

15 years

Found this part of copying & pasting very useful & time saving...

Member for

15 years

Found this part of copying & pasting very useful & time saving...

Member for

15 years 3 months

Hmmm... just had a look in Asta, you can definately copy across the library items for filters and sorts but i cannot see a way of copying an entire view across. Perhaps you could create a template out of the programme containing the view you want for use in the future but that doesn't much help with a programme which is already in existence.

Member for

15 years 6 months

Have you tried opening the programme you want to copy from and the one you want to copy to? Make sure the LIBRARY view is open on both programmes then left click and drag from the programme it is in to the LIBRARY view of the other programmes. You may be able to right click, copy and paste.

 

Regards 

Jonathan