Asta Powerproject Member for 15 years 11 months Member for 15 years 11 months Submitted by Andrew Willard on Wed, 2011-09-07 11:00 Permalink Hi Marinus,You can't progress Hi Marinus, You can't progress a demnad allocation. The allocation needs to be of type permanentscheduledallocation. You can then set the effort percent complete Regards Andrew Log in or register to post comments
Member for 15 years 11 months Member for 15 years 11 months Submitted by Andrew Willard on Wed, 2011-09-07 11:00 Permalink Hi Marinus,You can't progress Hi Marinus, You can't progress a demnad allocation. The allocation needs to be of type permanentscheduledallocation. You can then set the effort percent complete Regards Andrew
Member for
15 years 11 monthsHi Marinus,You can't progress
Hi Marinus,
You can't progress a demnad allocation. The allocation needs to be of type permanentscheduledallocation. You can then set the effort percent complete
Regards
Andrew