Asta Powerproject Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sat, 2008-11-01 12:34 Permalink RE: Planned Percent Complete Hi Laurie The easiest way is to set up your main programme as a "baseline" using the baseline wizard under the "file heading". When you set up the Planned Percent Complete column you can select the results to come from the baseline programme. You may need to go back to your first unprogressed programme to set up the 1st baseline and ten import it into your progressed charts. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sat, 2008-11-01 12:34 Permalink RE: Planned Percent Complete Hi Laurie The easiest way is to set up your main programme as a "baseline" using the baseline wizard under the "file heading". When you set up the Planned Percent Complete column you can select the results to come from the baseline programme. You may need to go back to your first unprogressed programme to set up the 1st baseline and ten import it into your progressed charts. Best regards Mike Testro
Member for
19 years 10 monthsRE: Planned Percent Complete
Hi Laurie
The easiest way is to set up your main programme as a "baseline" using the baseline wizard under the "file heading".
When you set up the Planned Percent Complete column you can select the results to come from the baseline programme.
You may need to go back to your first unprogressed programme to set up the 1st baseline and ten import it into your progressed charts.
Best regards
Mike Testro