Foster Wheeler Senior Planner

Woodside
Pluto LNG
Laem Chabang, Thailand (TOC (Thailand Operating Centre))
Senior Planning Engineer
With Worley Parsons a joint venture (FWW)
Australian $12 billion LNG Project the fastest developed LNG project from discovery of gas field in 2005 to first gas in late 2010.
Onshore infrastructure comprises a single LNG processing train with a forecast production capacity of 4.3 million tonnes a year. The LNG train is being fabricated in Thailand and shipped to site in 264 modules and supporting structures, including four 930 tonne Gas Turbine Generators.

Based at the module fabrication yard in Thailand as Progress & Reporting Coordinator responsible for producing high quality detailed and executive summary reporting daily, weekly and monthly; present advice up to management and Client.
Manage the input of contractor, subordinates and colleagues necessary to complete the tasks.
Keeping Management and Client informed about progress and any curative actions required for maintaining schedule and progress.
Database (MS Access), Operation, Maintenance and Development to insure accurate transfer of information from contractor and engineering centres.
Monthly level III Primavera Schedule updates.
Cover the responsibilities of the Planning Manager in their absence.