Fluor Planning Manager

As the Fluor Daniel/Consortium Planner I was responsible for the planning, scheduling and co-ordination of all parties working on the explosion damage at the Mossgas Refinery. This included three major contractors, Fluor Daniel’s director work force, numerous sub contractors and the refinery’s own work force, on demolition, design, procurement, fabrication, erection and commissioning activities. This project included civil, structural, mechanical, piping, electrical and instrumentation works.