I/E Planner, Redpath Engineering Services Ltd., Sable Island Gas Platform

START Date
END Date
Experience Hours (Planning & Scheduling)
2000

I/E Planner for the construction of the Thebaud Topsides Facilities for the Sable Gas Platform at Kvaerner’s Port Clarence yard. Responsible for updating the P3 plans, cable schedules and job cards etc. to produce weekly productivity and progress reports by discipline.

Dewsbury Civil Engineering Planner

Experience gained on Highways works which included assisting in supervision of site works, collating utility drawings (electric, gas, water & telecoms) for work packs (cable tv works), assign of work packs to gangs, surveying new works for tender & updating of progress made.

Duties included:
•Checking utility drawings to ensure information was correct.
•Going on site before digging work commenced to mark where clients ducting and chambers should be.
•Locate and mark any other utility in the vicinity using a RD400

K Home International Planner

•     Creation and development of Systems and procedures for planning, estimating, project control, cost control and implementation into the company standards.
•     Training and development of numerous staff including all the cost engineers/Project Services Engineers and Planning Personnel
•     Capital Cost Estimation with Icarus Project Manager to Price capital cost/Bulk Equipment for a Target Cost Construction Tenders and to aid procurement

Planner

Scheduled, monitored and inspected all work from start to completion
•     Creating programmes at level 1 and 3 to be used to aid design and construction.
•     Resource Scheduling producing level 3 manning Requirement throughout the duration of design and thought the construction to aid the term contractor
•     Revising network diagrams to be used for construction (using MS Visio)