I am also having the same problem, when i import the project P6 schedule to Pertmaster, the plan finish dates are going beyond the dates in the original schedule. I have tried to use 24 hrs unit time etc etc but still the problem persists. Can anyone help if they also had the same problem and solved it?
Much appreciated in advance.
Vimal
Member for
16 years
Member for16 years
Submitted by Roland Tannous on Sun, 2011-02-20 20:04
One additional note, even after choosing the right calendar from "Plan Menu ---> Calendars" , you must also pay attention that if your original Project in MSP or P6 contained Exception Days (like holidays or whatever) , Pertmaster doesn't import these correctly (at least if its an MSP Project) and you might have to reinput the Exceptions manually under "Plan Menu---> Calendars" as well.
Best Regards,
Roland
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Mon, 2011-02-14 13:39
Problem:
Activities are scheduled incorrectly when importing an MSP or Primavera project into Pertmaster 8.5.
Problem:
Non-working time is incorrect when importing a project into Pertmaster 8.5.
Cause:
When a project is imported into Pertmaster, the “7 Day” calendar is assigned to all resources. In Pertmaster 8.5, this calendar defaults to having working time from 9:00-16:00 when scheduling in hours. Therefore, if a project is imported using “Hour” or “Quarter Hour” as the planning unit, any activities with resources assigned will only be scheduled from 9:00-16:00 due to the resource availability.
Fix: Workaround: Edit the “7 Day” calendar so that each day has 24 hours of working time.
Remember that when activities and resources have different but compatible calendars activity will be scheduled when resource calendar allows for it to be performed within activity calendar, this before and after resource leveling. Even dummy resources for cost distribution can have this effect.
When you import P6 XER into Pertmaster, it also imports the calendars. P6 calendar allows the user to modify work / non work period every 30 mins i.e. :00-:30, :30-:60; this is not aligned with Pertmaster calendar settings (set work / non work every hour) hence total work hours may vary (though not significant). I suspect this has to do with conflict in Pertmaster and P6 settings, but I cannot put a finger on what it is. I changed the task calendar in Pertmaster but it didn’t work.
PP your email and I’ll send you screen shots..
I do not resource level, so I don’t see how it’s part of the problem.
Member for
24 years 9 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Sun, 2011-02-13 17:32
Then I have no idea nor way to be of any further help. All I remember from when I was a P3e user, now P6, and at the same time a P3 and SureTrak user is that when transferring files issues with the planning unit were well known.
The common solution was through a global change formula while for lags the only way was by manual adjustment. Then after these adjustments, usually dates would be equal before resource leveling, after resource leveling obviously not necessarily equal as each had their own different algorithm.
Member for
11 years 10 monthsHi,I am also having the same
Hi,
I am also having the same problem, when i import the project P6 schedule to Pertmaster, the plan finish dates are going beyond the dates in the original schedule. I have tried to use 24 hrs unit time etc etc but still the problem persists. Can anyone help if they also had the same problem and solved it?
Much appreciated in advance.
Vimal
Member for
16 yearsHello, Rafael has the right
Hello,
Rafael has the right answer.
One additional note, even after choosing the right calendar from "Plan Menu ---> Calendars" , you must also pay attention that if your original Project in MSP or P6 contained Exception Days (like holidays or whatever) , Pertmaster doesn't import these correctly (at least if its an MSP Project) and you might have to reinput the Exceptions manually under "Plan Menu---> Calendars" as well.
Best Regards,
Roland
Member for
21 years 8 monthsFrom: http://primavera.zxlm.c
From:
http://primavera.zxlm.cn/kb/prim73918
Permaster 8.5
Problem:
Activities are scheduled incorrectly when importing an MSP or Primavera project into Pertmaster 8.5.
Problem:
Non-working time is incorrect when importing a project into Pertmaster 8.5.
Cause:
When a project is imported into Pertmaster, the “7 Day” calendar is assigned to all resources. In Pertmaster 8.5, this calendar defaults to having working time from 9:00-16:00 when scheduling in hours. Therefore, if a project is imported using “Hour” or “Quarter Hour” as the planning unit, any activities with resources assigned will only be scheduled from 9:00-16:00 due to the resource availability.
Fix:
Workaround: Edit the “7 Day” calendar so that each day has 24 hours of working time.
Remember that when activities and resources have different but compatible calendars activity will be scheduled when resource calendar allows for it to be performed within activity calendar, this before and after resource leveling. Even dummy resources for cost distribution can have this effect.
Member for
18 years 9 monthsThanks Vladimir for the
Thanks Vladimir for the response... but
When you import P6 XER into Pertmaster, it also imports the calendars. P6 calendar allows the user to modify work / non work period every 30 mins i.e. :00-:30, :30-:60; this is not aligned with Pertmaster calendar settings (set work / non work every hour) hence total work hours may vary (though not significant). I suspect this has to do with conflict in Pertmaster and P6 settings, but I cannot put a finger on what it is. I changed the task calendar in Pertmaster but it didn’t work.
PP your email and I’ll send you screen shots..
I do not resource level, so I don’t see how it’s part of the problem.
Member for
24 years 9 monthsCheck if calendars are the
Check if calendars are the same (same work hours, same vacations).
With resource levelling the dates may be different but before resource they shall be same if calendars, durations and constraints are the same.
Member for
21 years 8 monthsThen I have no idea nor way
Then I have no idea nor way to be of any further help. All I remember from when I was a P3e user, now P6, and at the same time a P3 and SureTrak user is that when transferring files issues with the planning unit were well known.
The common solution was through a global change formula while for lags the only way was by manual adjustment. Then after these adjustments, usually dates would be equal before resource leveling, after resource leveling obviously not necessarily equal as each had their own different algorithm.
Best regards,
Rafael
Member for
18 years 9 monthsDavilla, Durations don't
Davilla,
Durations don't change, only the dates chane. For eg, you have 8 hours duration, but the dates will show 2 days...
Member for
21 years 8 monthsDo the duration of activities
Do the duration of activities changed? If so, by a factor of about 8?
Member for
18 years 9 monthsHey Matt, I have the same
Hey Matt,
I have the same problem, and was wondering if you got a response or eventually solved it. Please let me know. Thanks
If