Project Management Issues Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2011-09-04 05:49 Permalink Hi Tanveer a) Adjust the Hi Tanveer a) Adjust the logic - work patterns - resources within reasonable limits. b) Following a resource levelling excercise the project will probably take longer to complete. c) Reschedule the project All of the above depends on the quality of your programme. If you have any artificial constraints - FF SS Links - Lead lags - Top down scheduling - then you will get a false result. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Sun, 2011-09-04 05:49 Permalink Hi Tanveer a) Adjust the Hi Tanveer a) Adjust the logic - work patterns - resources within reasonable limits. b) Following a resource levelling excercise the project will probably take longer to complete. c) Reschedule the project All of the above depends on the quality of your programme. If you have any artificial constraints - FF SS Links - Lead lags - Top down scheduling - then you will get a false result. Best regards Mike Testro
Member for
19 years 10 monthsHi Tanveer a) Adjust the
Hi Tanveer
a) Adjust the logic - work patterns - resources within reasonable limits.
b) Following a resource levelling excercise the project will probably take longer to complete.
c) Reschedule the project
All of the above depends on the quality of your programme.
If you have any artificial constraints - FF SS Links - Lead lags - Top down scheduling - then you will get a false result.
Best regards
Mike Testro