how primavera calculate summary duration -wbs ?

Member for

19 years 11 months

hi, all

    When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar.

Best Regards

Member for

17 years 6 months

in P6 version 7 ,,,,  you have to have tick a global default calender,

may next version have this option which you  wants,

Member for

16 years 9 months

make default global equals project calendar 

in p6v7 project calendar can be tick as basis of summary

Member for

18 years

Thanks Michael 

 

is there alternative way to avoid using default calendar

Member for

16 years 9 months

check your assigned global calendar

p6 summary duration are based on global calendar (not project)

Member for

16 years 9 months

check your assigned global calendar

p6 summary duration are based on global calendar (not project)