Oracle Primavera - PM6 Member for 15 years 8 months Member for 15 years 8 months Submitted by Khuong Do on Thu, 2017-07-13 04:52 Permalink Hi,I write an article Hi, I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band. If you're interested kindly read here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/ Member for 19 years 11 months Member for 19 years 11 months Submitted by niles luo on Thu, 2010-11-11 09:29 Permalink hi, all When P6v7 hi, all When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar. Best Regards Member for 17 years 6 months Member for 17 years 6 months Submitted by Shazia khan on Thu, 2010-11-11 05:43 Permalink in P6 version 7 ,,,, you in P6 version 7 ,,,, you have to have tick a global default calender, may next version have this option which you wants, Member for 16 years 9 months Member for 16 years 9 months Submitted by michael ramos on Wed, 2010-11-10 15:42 Permalink make default global equals make default global equals project calendar in p6v7 project calendar can be tick as basis of summary Member for 18 years Member for 18 years Submitted by Alaa Al haj on Wed, 2010-11-10 14:00 Permalink Thanks Michael is there Thanks Michael is there alternative way to avoid using default calendar Member for 16 years 9 months Member for 16 years 9 months Submitted by michael ramos on Tue, 2010-11-02 09:30 Permalink check your assigned global check your assigned global calendar p6 summary duration are based on global calendar (not project) Member for 16 years 9 months Member for 16 years 9 months Submitted by michael ramos on Tue, 2010-11-02 09:30 Permalink check your assigned global check your assigned global calendar p6 summary duration are based on global calendar (not project) Log in or register to post comments
Member for 15 years 8 months Member for 15 years 8 months Submitted by Khuong Do on Thu, 2017-07-13 04:52 Permalink Hi,I write an article Hi, I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band. If you're interested kindly read here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/
Member for 19 years 11 months Member for 19 years 11 months Submitted by niles luo on Thu, 2010-11-11 09:29 Permalink hi, all When P6v7 hi, all When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar. Best Regards
Member for 17 years 6 months Member for 17 years 6 months Submitted by Shazia khan on Thu, 2010-11-11 05:43 Permalink in P6 version 7 ,,,, you in P6 version 7 ,,,, you have to have tick a global default calender, may next version have this option which you wants,
Member for 16 years 9 months Member for 16 years 9 months Submitted by michael ramos on Wed, 2010-11-10 15:42 Permalink make default global equals make default global equals project calendar in p6v7 project calendar can be tick as basis of summary
Member for 18 years Member for 18 years Submitted by Alaa Al haj on Wed, 2010-11-10 14:00 Permalink Thanks Michael is there Thanks Michael is there alternative way to avoid using default calendar
Member for 16 years 9 months Member for 16 years 9 months Submitted by michael ramos on Tue, 2010-11-02 09:30 Permalink check your assigned global check your assigned global calendar p6 summary duration are based on global calendar (not project)
Member for 16 years 9 months Member for 16 years 9 months Submitted by michael ramos on Tue, 2010-11-02 09:30 Permalink check your assigned global check your assigned global calendar p6 summary duration are based on global calendar (not project)
Member for
15 years 8 monthsHi,I write an article
Hi,
I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band. If you're interested kindly read here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/
Member for
19 years 11 monthshi, all When P6v7
hi, all
When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar.
Best Regards
Member for
17 years 6 monthsin P6 version 7 ,,,, you
in P6 version 7 ,,,, you have to have tick a global default calender,
may next version have this option which you wants,
Member for
16 years 9 monthsmake default global equals
make default global equals project calendar
in p6v7 project calendar can be tick as basis of summary
Member for
18 yearsThanks Michael is there
Thanks Michael
is there alternative way to avoid using default calendar
Member for
16 years 9 monthscheck your assigned global
check your assigned global calendar
p6 summary duration are based on global calendar (not project)
Member for
16 years 9 monthscheck your assigned global
check your assigned global calendar
p6 summary duration are based on global calendar (not project)