Hi Sanjay,



Try to change the resource type from labor to nonlabor by filtering all activities having the resource type of labor. Afterwards, select the "Assign Resource" command button located at your right corner of your screen.



Select the resource name and select replace then assign the new resource type (labor). This cannot be done for the activities that has already actual.



Hope this helps.



Regards,



Arnold