1. Change the "Timescale Start" of your project to the "Earliest Project Start" or "Custom Date" in File Menu --> Page Setup --> Options Tab. So that, your Data Date will become visible.
2. If I understood you, Performance % complete cannot be zero if you have resource cost loaded in your project. A lot of reasons. Cite an example and I will tell what is the reason.
Hope this helps.
Regards,
Arnold
Member for
17 years 9 months
Member for17 years9 months
Submitted by Shahzad Ahmad on Thu, 2009-04-09 01:00
Member for
17 years 9 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hello Mr.Arnold
I have sent to primavera6@live.com
Thanks & best Regards
Shahzad
Member for
18 years 6 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hi Shahzad,
No..That is not my email address anymore..Here is my email add. primavera6@live.com
Thanks.
Regards,
Arnold
Member for
17 years 9 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
yes i sent it to you p3-fer@sixco.ae
Member for
18 years 6 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
No Problem. Did you send the .xer file?
Member for
17 years 9 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hi -Arnold
I am sorry i did not know abouted ..about capital latters..
Thanks & kind regards for all Planners.
Member for
18 years 6 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hi Shahzad,
Yes, you can send it to me including the project layout.
Please next time do not capitalize all the letters. As if you are trying to shout all the Planners.
Thanks.
Arnold
Member for
17 years 9 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hello -Arnold
Data Date line still not printable while i change the TS , TS =PS (time scale start is EPS)
TF = PF ( timescale finish is Project Finish)
TS WITH IN 3 LINE
2. PERFORMANCE % COMPLETE
PROJECT SCHEDULE WITH OUT RESOURCES IT IS CLIENT REQUEST TO AVOID CLAME.
ITs BASED ON MANUAL UPDATE schedule.
( IN MY TRAINING MANUAL SAYS PhY % COULD NOT ROOLED UP..)
Could i send you my schedule by email for the setting.
Regards
Shahzad
Thanks
Shahzad
Member for
18 years 6 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hi Shahzad,
1. Change the "Timescale Start" of your project to the "Earliest Project Start" or "Custom Date" in File Menu --> Page Setup --> Options Tab. So that, your Data Date will become visible.
2. If I understood you, Performance % complete cannot be zero if you have resource cost loaded in your project. A lot of reasons. Cite an example and I will tell what is the reason.
Hope this helps.
Regards,
Arnold
Member for
17 years 9 monthsRE: DTATA DATE DISAPPEAR IN PRINTING
Hi ..Rashid
I did the same.
Coverted in PDF then Print DATA DATE LINE is Printed.
Thanks
Shahzad