DTATA DATE DISAPPEAR IN PRINTING

Member for

17 years 9 months

Hi -Arnold



I am sorry i did not know abouted ..about capital latters..





Thanks & kind regards for all Planners.


Member for

18 years 6 months

Hi Shahzad,



Yes, you can send it to me including the project layout.



Please next time do not capitalize all the letters. As if you are trying to shout all the Planners.



Thanks.



Arnold

Member for

17 years 9 months

Hello -Arnold



Data Date line still not printable while i change the TS , TS =PS (time scale start is EPS)



TF = PF ( timescale finish is Project Finish)



TS WITH IN 3 LINE





2. PERFORMANCE % COMPLETE



PROJECT SCHEDULE WITH OUT RESOURCES IT IS CLIENT REQUEST TO AVOID CLAME.



ITs BASED ON MANUAL UPDATE schedule.



( IN MY TRAINING MANUAL SAYS PhY % COULD NOT ROOLED UP..)



Could i send you my schedule by email for the setting.



Regards

Shahzad



Thanks

Shahzad

Member for

18 years 6 months

Hi Shahzad,



1. Change the "Timescale Start" of your project to the "Earliest Project Start" or "Custom Date" in File Menu --> Page Setup --> Options Tab. So that, your Data Date will become visible.



2. If I understood you, Performance % complete cannot be zero if you have resource cost loaded in your project. A lot of reasons. Cite an example and I will tell what is the reason.



Hope this helps.



Regards,



Arnold

Member for

17 years 9 months

Hi ..Rashid



I did the same.



Coverted in PDF then Print DATA DATE LINE is Printed.



Thanks

Shahzad