PROJECT FINISHED DATE NOT CHANGING.

Member for

17 years 9 months

Hello Mr.Diego



Thanks for your reply.



This is valid reply from you in my schedule all updated activity are not critical thats why finished date of project not reflecting.





Best Regards



Shahzad




Member for

16 years 7 months

Hi Shazad



Your project completion date will only change if an activity in the critical path changes.

You can have a delivery or future event dictating the completion date of your project, and if so, you can commence all the activities aerlier that you want to, but the critical path will remain unchanged.