Your project completion date will only change if an activity in the critical path changes.
You can have a delivery or future event dictating the completion date of your project, and if so, you can commence all the activities aerlier that you want to, but the critical path will remain unchanged.
Member for
17 years 9 monthsRE: PROJECT FINISHED DATE NOT CHANGING.
Hello Mr.Diego
Thanks for your reply.
This is valid reply from you in my schedule all updated activity are not critical thats why finished date of project not reflecting.
Best Regards
Shahzad
Member for
16 years 7 monthsRE: PROJECT FINISHED DATE NOT CHANGING.
Hi Shazad
Your project completion date will only change if an activity in the critical path changes.
You can have a delivery or future event dictating the completion date of your project, and if so, you can commence all the activities aerlier that you want to, but the critical path will remain unchanged.