Storing Activities in P6 then reusing?

Member for

18 years 6 months



Sorry, I didn’t understood correctly. What do you mean? You want to change the name of the activities?


Member for

19 years 5 months

one more quick question - How do I change the name of the strings of activities I group into Methodology Management - it has a a name I want to change but I can’t figure out how to do it

Member for

18 years 6 months

Hi Nicholas,



Go to Start --> Programs --> Primavera --> Methodology Management.



Login Name: "admin"

Password: "admin"



Regards,



Arnold

Member for

19 years 5 months

Arnold - where is Methodology Management? I have exported the file of the activities I need but am not sure how to import it in?



I looked at the plug in / select base and have understood how to ’add’ saved activity groups - just not sure where Methodology Management is?

Member for

18 years 10 months

Christopher



To copy activities I use a different technique.

1. Creat a WBS-node "To_Copy"

2. Copy the required activities into "To_Copy"

3. Goto view "WBS"

4. Copy or move "To_Copy" into the new project

5. Arrange the activities within the new project.



That’s all.



Regards and good luck!

Dieter

Member for

17 years 9 months

HELLO-MR.PUY



Prob. related to P6



Please advise me as below.



I have made schd. there is % complte type is "Duration" for all activity.



The Schd.i want to update manually with physical % complete.



1. I have to chnage all activity (% complete type) before start updating or one by one i means while updating activity ,then i will change % complete type "duration " in to "physical" then put actual start, % and remaining duration.



in that case updated activity completed/under progress will be

(%Physical) and unupdate activity will be

( % Duration TYpe)



in the P6 manual says have to set at intial stage, means default ..% complete type.



(if i will change % complte type then it has to be same in Baseline & Current Project m I right)



Thanks

Shahzad

Member for

18 years 6 months

Hi Christopher,



You need to create a new project in Methodology Management or you can import the project you needed to restore and use it in the future.



Try the following steps:



1. If you have already existing activities or group of activities to be used for future reference, select all the group of activities and save it. delete all the others which is not part of that group. Or you can save everything without deleting the others.

2. After complying the #1, Go to File Menu --> Export.

3. Open the Methodology Management.

4. In the File Menu --> Import the project you exported from Project Management.

5. Then follow the window wizard.



Now you have already finished storing those activities.



Here are the steps on how to re-use or retrieve the group of activites.



1. Go to File Menu --> Project Architect and follow the window wizard.

2. In "Select Base or Plug-in" tick the "Base Methodology" then Next.

3. In Select Base Methodology, select "Select Base"

4. Mark the checkbox next to the "Methodology Name" then close.

5. In "Tailor WBS" select ’Tailor’ you can select the WBS Code you wanted to copy or select the "Activities" to be included by "ticking & unticking" the checkbox.

6. In ’Save Location" select the WBS Element radio button and select or locate the newly added WBS or Activities to your current project.



Hope this helps.



Cheers,



Arnold