Oracle Primavera - PM6 Member for 17 years 6 months Member for 17 years 6 months Submitted by James Braghini on Thu, 2009-03-05 11:28 Permalink RE: Remaining duration: retaining actual cost Your the man as usual. Thanks, James B. Member for 18 years 10 months Member for 18 years 10 months Submitted by Dieter Wambach on Thu, 2009-03-05 11:23 Permalink RE: Remaining duration: retaining actual cost James Yes. For your information: Check the parameter settings in view "Projects" under tab "Resources" on the right. Regards Dieter Log in or register to post comments
Member for 17 years 6 months Member for 17 years 6 months Submitted by James Braghini on Thu, 2009-03-05 11:28 Permalink RE: Remaining duration: retaining actual cost Your the man as usual. Thanks, James B.
Member for 18 years 10 months Member for 18 years 10 months Submitted by Dieter Wambach on Thu, 2009-03-05 11:23 Permalink RE: Remaining duration: retaining actual cost James Yes. For your information: Check the parameter settings in view "Projects" under tab "Resources" on the right. Regards Dieter
Member for
17 years 6 monthsRE: Remaining duration: retaining actual cost
Your the man as usual.
Thanks,
James B.
Member for
18 years 10 monthsRE: Remaining duration: retaining actual cost
James
Yes.
For your information: Check the parameter settings in view "Projects" under tab "Resources" on the right.
Regards
Dieter