Oracle Primavera - PM6 Member for 17 years Member for 17 years Submitted by sonia rose on Tue, 2009-02-10 13:05 Permalink RE: WBS duration Thanks Raviraj Member for 18 years 5 months Member for 18 years 6 months Submitted by A D on Tue, 2009-02-10 11:17 Permalink RE: WBS duration Thats because WBS Durations are based on global calendar and not project calendar. Ur global calendar must be set for 5 days a week. The issue is still not resolved by primavera and is on the list. Cheers, Rav Log in or register to post comments
Member for 17 years Member for 17 years Submitted by sonia rose on Tue, 2009-02-10 13:05 Permalink RE: WBS duration Thanks Raviraj
Member for 18 years 5 months Member for 18 years 6 months Submitted by A D on Tue, 2009-02-10 11:17 Permalink RE: WBS duration Thats because WBS Durations are based on global calendar and not project calendar. Ur global calendar must be set for 5 days a week. The issue is still not resolved by primavera and is on the list. Cheers, Rav
Member for
17 yearsRE: WBS duration
Thanks Raviraj
Member for
18 years 5 monthsRE: WBS duration
Thats because WBS Durations are based on global calendar and not project calendar.
Ur global calendar must be set for 5 days a week. The issue is still not resolved by primavera and is on the list.
Cheers,
Rav