Regarding (EPC) Engineering, Procurement, Costruction.

Depending on the field, if you were only working to define the Engineering aspect. You would tipically use detail from the engineering department to develop your WBS. Example:

Project Management

Pipeline

Facilities

Hydraulics

Electrical

Survey

ROW

Each department should be able to provide you with details that will help you establish the activities, manhours, expenses needed that will fall under these categories.