Percent Complete in P3

Member for

17 years 3 months

Although P3 allows entry of % completion even without the specified actual dates, I guess P3 users never do such a thing in the schedule as one will noticeably be viewing a dangling blue colored bar beyond the data date. To answer the question;



Adverse effect on the schedule:

- You will unnecessarily consume the resource allocation of the activity which will affect as well the program’s cost calculations.



Adverse effect on the planner:

- You will be tagged as a "STUPID PLANNER".



Cheers!!!