Although P3 allows entry of % completion even without the specified actual dates, I guess P3 users never do such a thing in the schedule as one will noticeably be viewing a dangling blue colored bar beyond the data date. To answer the question;
Adverse effect on the schedule:
- You will unnecessarily consume the resource allocation of the activity which will affect as well the programs cost calculations.
Member for
17 years 3 monthsRE: Percent Complete in P3
Although P3 allows entry of % completion even without the specified actual dates, I guess P3 users never do such a thing in the schedule as one will noticeably be viewing a dangling blue colored bar beyond the data date. To answer the question;
Adverse effect on the schedule:
- You will unnecessarily consume the resource allocation of the activity which will affect as well the programs cost calculations.
Adverse effect on the planner:
- You will be tagged as a "STUPID PLANNER".
Cheers!!!