S Curve and Graphical Reports in p5 or p6

Member for

17 years 11 months

The best way I’ve found....



Use SDK (API, direct SQL link, etc...) to get the TASK_SPREAD, RSRC_SPREAD, or WBS_SPREAD Tables, you can then grab the EV, PV, and AC by month or financial period... then create the s-curves someplace else... access,crystal,excel...



Or... you can spend $25k on Primavera’s new ERD (Enterprise Reporting Database) that seems to pull the information the same way...



I don’t know what the other posts suggest... but I’ve found graphical reports to be significantly lacking in P6.. which is why I think Primavera themselves recommend crystal anytime you start wanting better reporting...

Member for

17 years 4 months

Well David, i ve checked and found something but that is not really as good as in p3, that is like viewing and like monitoring resources or costs, shortly what i got is in p5 or p6 graphical reports doesnt exist.

Member for

21 years

Kamil,



There have been SO MANY posts about this, I am not surprised that no-one has retyped the instructions! Perhaps you could use the "search" facility and I am sure you will find the right instructions - otherwise I am sure you will post again!