Graphs & S Curves

Member for

19 years 6 months

Shiv,



To do a global change....



(1) In "Select Subject Area" choose "Activity Resource Assignments"

(2)Where - Resource ID Name = (your target resource)

Then - Budget Labour Units = Budget Labour Units x 0.9



Check the result is what you expected and commit.



David