Oracle Primavera - PM6 Member for 18 years 6 months Member for 18 years 6 months Submitted by Arnold Puy on Wed, 2008-05-21 14:42 Permalink RE: importing activities from excel James, Perhaps, it is because you did not assign Activity Codes or define WBS in your Activities. Try to do this in excel or by using Global Change or even by dragging your activities to their respective groups. Arnold Log in or register to post comments
Member for 18 years 6 months Member for 18 years 6 months Submitted by Arnold Puy on Wed, 2008-05-21 14:42 Permalink RE: importing activities from excel James, Perhaps, it is because you did not assign Activity Codes or define WBS in your Activities. Try to do this in excel or by using Global Change or even by dragging your activities to their respective groups. Arnold
Member for
18 years 6 monthsRE: importing activities from excel
James,
Perhaps, it is because you did not assign Activity Codes or define WBS in your Activities. Try to do this in excel or by using Global Change or even by dragging your activities to their respective groups.
Arnold